- Type
- Boiler flue
- Location
- Redditch, West Midlands
- Status
- Complete
- System
- Twin wall insulated flue
The job
Three boilers and a clean roof finish.
We designed, supplied and installed a new boiler flue at The Vaynor First School in Redditch.
Three 110kW gas boilers connect into a Ø150 twin wall insulated header. The header runs about 4 metres, then rises about 6 metres through the roof.
Inside, the riser sits on a base tee with a drain and is held on strut fixed to the wall. On the roof, the stack has a mesh terminal and a strut bracket back to the upstand.
3 × 110kW
boilers on one header
6m
approximate stack height
On site.
Site photographs. Tap a photo to see it larger.
Scope
What we delivered.
- Flue design
- Ø150 twin wall insulated header
- Base tee with drain and strut supports
- Roof terminal with mesh and stay bracket
Project details
- Boiler flue
- West Midlands