The job
Boilers and water heaters up a dedicated riser.
We designed, supplied and installed the flues for a new plant room at Prince Albert School in Birmingham.
Four 175kW condensing boilers connect with Ø180 primaries into a Ø300 header. Three 123kW water heaters connect with Ø130 primaries into a Ø250 header.
Both headers rise about 13 metres to roof level inside a dedicated flue riser, and finish with self supporting stainless terminals at least 3 metres above the roof.
7
appliances on two headers
13m
approximate stack height
On site.
Site photographs. Tap a photo to see it larger.
Scope
What we delivered.
- Flue design
- Ø180 boiler primaries into a Ø300 header
- Ø130 water heater primaries into a Ø250 header
- Headers hung from drop rods and strut
- Self supporting roof terminals