- Type
- Boiler flue
- Location
- Maidstone, South East
- Status
- Complete
- System
- Twin wall insulated flue
The job
Two flue headers for a farm plant room.
We designed, supplied and installed the boiler and water heater flues in a new plant room at Ledian Farm near Maidstone in 2021.
Three 320kW boilers connect into one shared header, and three 100kW water heaters connect into a second, smaller header. Each system rises about 10 metres.
The headers run at high level, hung from the soffit on drop rods and strut, and leave the room through a formed opening in the wall.
3 × 320kW
boilers on one header
3 × 100kW
water heaters on a second header
On site.
Site photographs. Tap a photo to see it larger.
Scope
What we delivered.
- Flue design and route drawing for approval
- Boiler header and primaries
- Water heater header
- Drop rod and strut supports
- Job specific RAMS
- O&M file and certificate of conformity
Project details
- Boiler flue
- South East
- Design, supply and install