- Type
- Generator exhaust
- Location
- Coventry, West Midlands
- Status
- Complete
- System
- Insulated twin wall exhaust
The job
An exhaust stack for a standby generator.
We designed, supplied and installed the exhaust flue for a 610kVA standby generator at a factory in Coventry in April 2022.
The exhaust leaves the top of the generator enclosure and rises about 4 metres in insulated twin wall flue, Ø200 inside, so it discharges well clear of the unit.
We surveyed the site, drew the route in CAD and fitted it with our own fixings and supports.
610kVA
standby generator
Ø200
insulated exhaust flue
On site.
Site and survey photographs. Tap a photo to see it larger.
Scope
What we delivered.
- Site survey
- Calculations and CAD drawing
- Job specific RAMS
- Insulated twin wall exhaust, Ø200
- Strut supports and fixings
- Certificate of conformity
Project details
- Generator exhaust
- West Midlands
- Design, supply and install