- Type
- Boiler flue
- Location
- Glasgow, Scotland
- Status
- Complete
- System
- Twin wall insulated flue
The job
Two steam boiler flues through a factory roof.
We designed, supplied and installed separate flues for two steam boilers at a waste treatment site in Glasgow.
Each boiler connects through a 45° elbow into a 135° tee, with a soot collector and drain at the base of each stack. The flues are twin wall insulated, Ø300 inside and Ø360 outside.
Both stacks rise through the roof to open terminals with mesh guards, 3 metres above roof level. We also supplied and fitted the combustion air ducting.
2
steam boiler flues
Ø300
twin wall insulated
3m
terminals above roof level
On site.
Survey photographs. Tap a photo to see it larger.
Scope
What we delivered.
- Site survey and sketch
- Flue calculations and CAD drawing
- Twin wall insulated flues, Ø300, one per boiler
- Supports and fixings
- Open mesh terminals 3 metres above the roof
- Combustion air ducting
Finishing
The details we leave behind.
Soot collector with drain at the base of each stack.
Project details
- Boiler flue
- Scotland
- Design, supply and install