The job
Three boiler flues, old ones out.
New flues for three 60 kW boilers in the EOS Building at a factory site in Derby, with the old flue taken out.
Each boiler has its own Ø100 twin wall insulated flue with two elbows.
3
60 kW boilers
Ø100
twin wall insulated flues
On site.
Site photographs. Tap a photo to see it larger.
Scope
What we delivered.
- Site survey
- CAD drawing
- Old flue taken out
- Three Ø100 twin wall insulated flues
- strut channel supports and fixings
Project details
- Boiler flue
- East Midlands
- Supply and install