The job
Designed and built on the day.
New flues for three 120 kW boilers in Plant Room 3 at Reading Hospital.
The new boiler spigots weren't where the old ones had been, so we designed and built the route on site to keep alignment, fall and clearances.
We stripped out the old flue, set strut channel supports and finished the install the same day, working on into the evening.
Ø150 primaries into a Ø250 header and riser.
3
120 kW boilers
Ø250
header and riser
On site.
Survey photographs. Tap a photo to see it larger.
Scope
What we delivered.
- Old flue stripped out
- strut channel supports
- Ø150 boiler primaries
- Ø250 twin wall insulated header and riser
- Certificate of conformity