The job
Biomass flue works at a Wisbech plant.
We designed, supplied and installed additional flue works at a biomass plant in Wisbech.
A Ø400 twin wall insulated flue takes the gas from the bag filter to the fan. It runs about 1.5 metres, turns 90 degrees, runs about 3 metres, turns down and drops about 4.4 metres, then turns into the fan inlet.
Work on the existing stacks was done from a truck mounted cherry picker.
Ø400
twin wall insulated flue
4.4m
vertical drop to the fan
On site.
Site photographs. Tap a photo to see it larger.
Scope
What we delivered.
- Flue design
- Ø400 twin wall flue from bag filter to fan
- Truck mounted cherry picker for the stack work
Project details
- Industrial chimney
- East of England
- Design, supply and install
Got a job like this?