The job
Two boiler flues up the outside of the lab.
We designed, supplied and installed two new flues for the existing 500kW boilers at Plymouth Marine Laboratory in spring 2023.
Each Ø300 twin wall flue runs through the plant room on drop rod supports and leaves the building above the louvred plant room door.
Outside, the pair turn up the face of the building and rise side by side about 20 metres, held on wall brackets. Each flue has a test point, a drain and a draught stabiliser.
2 × 500kW
boilers
20m
approximate rise up the building
Ø300
twin wall insulated flues
On site.
Site photographs. Tap a photo to see it larger.
Scope
What we delivered.
- Site survey
- Flue calculations and CAD drawing
- Job specific RAMS
- Two twin wall insulated flues, Ø300
- Drop rod supports inside, wall brackets outside
- Test points, drains and draught stabilisers
- Technical submittal and O&M documents
Project details
- Boiler flue
- South West
- Design, supply and install