Two polished stainless flues leaving a plant room door and rising side by side up a five storey aggregate-faced building
All projects
Boiler flues GE2722

Plymouth Marine Laboratory

Plymouth, boiler flues

Type
Boiler flue
Location
Plymouth, South West
Status
Complete
System
Twin wall insulated flue

The job

Two boiler flues up the outside of the lab.

We designed, supplied and installed two new flues for the existing 500kW boilers at Plymouth Marine Laboratory in spring 2023.

Each Ø300 twin wall flue runs through the plant room on drop rod supports and leaves the building above the louvred plant room door.

Outside, the pair turn up the face of the building and rise side by side about 20 metres, held on wall brackets. Each flue has a test point, a drain and a draught stabiliser.

2 × 500kW

boilers

20m

approximate rise up the building

Ø300

twin wall insulated flues

On site.

Site photographs. Tap a photo to see it larger.

Plymouth Marine Laboratory, Plymouth, boiler flues. The two flues rising up the building.
Plymouth Marine Laboratory, Plymouth, boiler flues. The flues leaving the plant room.
Plymouth Marine Laboratory, Plymouth, boiler flues. The pair on their drop rod supports.

Scope

What we delivered.

  • Site survey
  • Flue calculations and CAD drawing
  • Job specific RAMS
  • Two twin wall insulated flues, Ø300
  • Drop rod supports inside, wall brackets outside
  • Test points, drains and draught stabilisers
  • Technical submittal and O&M documents

Project details

  • Boiler flue
  • South West
  • Design, supply and install
Similar workBoiler flues

Got a job like this?

Price normally within 24 hours of drawings or survey information.

Send drawings Get a price