Two stainless twin wall flues coming out through wall louvres and rising up a clad factory wall
All projects
Air handling unit flues GE3145

Factory

Nottingham, air handling unit flues

Type
Process exhaust
Location
Nottingham, East Midlands
Status
Complete
System
Twin wall insulated flue

The job

Two new flues out through the louvres.

New flues for two air handling units at a factory in Nottingham.

The old flues went up through the roof. We took them out and ran the new flues sideways through the wall louvres, then up the outside of the building to finish 2m above.

Where the old flues came through the roof we left a short length in place with a bracket and capped the tops to keep the rain out. Each louvre got a flat finishing plate. The work was signed off on 10 December 2024.

2

air handling units

Ø130

twin wall insulated flue

4.5m

vertical per flue

3.5m

horizontal per flue

On site.

Site photographs. Tap a photo to see it larger.

Factory, Nottingham, air handling unit flues. The two flues leave through the louvres and rise up the wall.
Factory, Nottingham, air handling unit flues. The flue run inside, hung on drop rods.

Scope

What we delivered.

  • Site survey and CAD drawing
  • Old flues taken out and disposed of
  • Two twin wall flues through the louvres
  • Flat finishing plate at each louvre
  • strut channel supports and wall brackets
  • Certificate of conformity

Finishing

The details we leave behind.

A flat plate finishes each louvre opening, and the old roof openings are capped off against the weather.

Project details

  • Process exhaust
  • East Midlands
  • Supply and install
Similar workProcess exhaust

Got a job like this?

Price normally within 24 hours of drawings or survey information.